Old 01-25-2006, 12:56 AM
rayis rayis is offline
Novice
 
Join Date: Mar 2005
Location: United Arab Emirates
Posts: 1
rayis
Default Different % complete in Project Center & View a Project

First you check the field names, both should be either % Complete or % Work Complete. If you are looking % Complete in PWA and % Work Complete in Project Professional, the values will be different.


If that is not the case then, you have to do the following steps to align the % complete/% Work complete in Project Professional and PWA.

1. Open the project plan using project professional
2. Select |Collaborate | Publish | Republish Assignments
3. Check (tick) Overwrite actual work entered by resources
4. Click OK button

This action will push the values from Project Professional to PWA, including individual resource timesheets.

- Rayis
Reply With Quote
 

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Need some basic help on Project NewToProject Project 0 04-06-2008 07:03 AM
Error 9571 when opening Project Server from Project Pro mona Project 0 04-24-2007 07:50 AM
Different % complete in Project Center & View a Project Project Server 2003 SP2 Project 15 01-25-2007 03:52 AM
Creating new project Using PDS myanilkumar Project 0 01-05-2006 12:35 AM
Help: MS Project viewer obenix Office 2 05-06-2005 01:28 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:42 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft