First you check the field names, both should be either % Complete or % Work Complete. If you are looking % Complete in PWA and % Work Complete in Project Professional, the values will be different.
If that is not the case then, you have to do the following steps to align the % complete/% Work complete in Project Professional and PWA. 1. Open the project plan using project professional 2. Select |Collaborate | Publish | Republish Assignments 3. Check (tick) Overwrite actual work entered by resources 4. Click OK button This action will push the values from Project Professional to PWA, including individual resource timesheets. - Rayis |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Need some basic help on Project | NewToProject | Project | 0 | 04-06-2008 07:03 AM |
| Error 9571 when opening Project Server from Project Pro | mona | Project | 0 | 04-24-2007 07:50 AM |
Project Server 2003 SP2
|
Project | 15 | 01-25-2007 03:52 AM | |
| Creating new project Using PDS | myanilkumar | Project | 0 | 01-05-2006 12:35 AM |
| Help: MS Project viewer | obenix | Office | 2 | 05-06-2005 01:28 AM |