Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 09-10-2024, 10:21 AM
vanmi vanmi is offline Baseline % Complete with RAG indicator Windows 10 Baseline % Complete with RAG indicator Office 2013
Novice
Baseline % Complete with RAG indicator
 
Join Date: Sep 2024
Posts: 1
vanmi is on a distinguished road
Default Baseline % Complete with RAG indicator

Good day Experts,
I'm trying to create a RAG indicator based on project progress. That is to RAG a work activity that is tracked against the predicated workload at time of observation (baseline estimate at that time), against the actual time delivered). For example, the baseline estimate is 20 days. At time 10 days the baseline estimate is (10/20) = 50% supposed to be completed. Then actual is e.g. 30% at time 10. Therefore the project has predicated to have slipped. The Red, Amber, Green should be able to be set for this measurement at a percentage level. If 0% variance or in front of delivery it is "GREEN", if it is 10% behind at time T, it is amber, and if it is more than 20% it is Red. Then also futher indicators that you would deem is the best way to determine the risk on delivery of the work activity
Reply With Quote
  #2  
Old 11-24-2024, 11:57 AM
ProjectPlanner's Avatar
ProjectPlanner ProjectPlanner is offline Baseline % Complete with RAG indicator Windows 10 Baseline % Complete with RAG indicator Office 2019
Advanced Beginner
 
Join Date: Mar 2021
Location: UK
Posts: 75
ProjectPlanner is on a distinguished road
Default

These 2 blog posts should help you.
  1. Microsoft Project Baseline Percent (%) with Weighted Summary Roll-up This will show you how to set-up a custom field for baseline %
  2. Microsoft Project Progress Status Traffic Light (RAG Status)This will show you how to set-up a RAG but instead of using the default % complete field as shown in the blog post, use the baseline % from #1 above for the RAG.
Reply With Quote
Reply

Tags
msp rag msproject



Similar Threads
Thread Thread Starter Forum Replies Last Post
20 day gap indicator Planner18 Project 3 03-23-2017 04:09 PM
Baseline % Complete with RAG indicator How to show planned% complete and actual% complete on the (Project Overview) dashboard report? zislam14 Project 3 12-17-2015 03:03 PM
Baseline % Complete with RAG indicator physical complete %, regular work, vs % complete ketanco Project 1 06-16-2014 11:08 AM
Baseline % Complete with RAG indicator Task Indicator - All predecessors complete true/false, y/n jdove78 Project 2 10-10-2012 05:53 PM
some work was complete at my baseline ketanco Project 1 01-25-2012 02:45 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 05:32 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft