Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 11-08-2024, 03:56 AM
Kübra Bilgin Kübra Bilgin is offline Automatic adjustment of job durations with weight information in steel fabrication project Windows 10 Automatic adjustment of job durations with weight information in steel fabrication project Office 2021
Novice
Automatic adjustment of job durations with weight information in steel fabrication project
 
Join Date: Nov 2024
Posts: 2
Kübra Bilgin is on a distinguished road
Default Automatic adjustment of job durations with weight information in steel fabrication project

Hello,
We are planning according to tonnage in steel manufacturing projects. We want to plan projects in Ms project. However, I want the tasks in the project to be planned automatically according to the weight entered. how can I do this?
Reply With Quote
  #2  
Old 11-08-2024, 08:10 PM
ineeju ineeju is offline Automatic adjustment of job durations with weight information in steel fabrication project Windows 10 Automatic adjustment of job durations with weight information in steel fabrication project Office 2021
Novice
 
Join Date: Jul 2022
Location: Seoul
Posts: 11
ineeju is on a distinguished road
Default

1. Enter weight in the [Number1] field.
2. Automatically display the Duration that matches the weight in the [Duration1] field(using a formula).
3. Copy the [Duration1] field value to the [Duration] field(Copy everything at once using a macro).

If this process is what you were thinking of and you need more details, please email me.
ineejuatyahoodotcom

P.S.
Is the smallest unit of weight 1 ton? How many days is 1 ton?
Reply With Quote
  #3  
Old 11-11-2024, 06:31 AM
Kübra Bilgin Kübra Bilgin is offline Automatic adjustment of job durations with weight information in steel fabrication project Windows 10 Automatic adjustment of job durations with weight information in steel fabrication project Office 2021
Novice
Automatic adjustment of job durations with weight information in steel fabrication project
 
Join Date: Nov 2024
Posts: 2
Kübra Bilgin is on a distinguished road
Default

Quote:
Originally Posted by ineeju View Post
1. Enter weight in the [Number1] field.
2. Automatically display the Duration that matches the weight in the [Duration1] field(using a formula).
3. Copy the [Duration1] field value to the [Duration] field(Copy everything at once using a macro).

If this process is what you were thinking of and you need more details, please email me.
ineejuatyahoodotcom

P.S.
Is the smallest unit of weight 1 ton? How many days is 1 ton?
One laborer works 4 days for 1 ton. How can I establish this relationship in Ms project?
Reply With Quote
  #4  
Old 11-28-2024, 11:35 PM
zeeqinsan zeeqinsan is offline Automatic adjustment of job durations with weight information in steel fabrication project Windows 11 Automatic adjustment of job durations with weight information in steel fabrication project Office 2021
Novice
 
Join Date: Nov 2024
Posts: 2
zeeqinsan is on a distinguished road
Default

The method I follow in steel calculation is as follows:

In the "Resource Name" section, I specify "Steel Works," then in the "Work" section, I enter the tonnage amount to be processed. Once I assign the number of days needed to complete the task in the "Duration" section, the "Resource Usage" section shows the daily distribution. Based on my daily processing capacity, I identify any excess and make manual adjustments. "Task Type= Fixed Work" should be selected.
Reply With Quote
Reply

Tags
automatic tenure



Similar Threads
Thread Thread Starter Forum Replies Last Post
weight of arrow przytula PowerPoint 1 12-19-2022 12:36 PM
Automatic adjustment of job durations with weight information in steel fabrication project Automatic adjustment date zbiku25 Project 3 02-28-2017 09:03 AM
Automatic adjustment of job durations with weight information in steel fabrication project showing fabrication items in schedule ketanco Project 4 06-24-2014 12:18 PM
Restricting Picture Border Weight in Word 2010 TheDarkCanuck Word 0 10-18-2012 08:55 AM
Automatic adjustment of job durations with weight information in steel fabrication project MS Project 2010 Durations not working seanpears99 Project 1 10-07-2011 07:28 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:45 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft