Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #1  
Old 03-23-2017, 02:49 AM
Planner18 Planner18 is offline 20 day gap indicator Windows 8 20 day gap indicator Office 2010 32bit
Novice
20 day gap indicator
 
Join Date: Oct 2014
Posts: 14
Planner18 will become famous soon enough
Default 20 day gap indicator

Hi All,



I'm looking for a formula that will indicate/highlight if the gap between two tasks is greater than 20 working days.

For example, Task A is the predecessor of task B and there must be a 20 working day gap between the two tasks. If the gap become greater than 20 working days, I need an indicator to highlight this against task B.

Does anyone have a formula to achieve this?

Any help would be appreciated

Cheers

Planner18
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
20 day gap indicator Office 2013: language indicator in the status bar? franklekens Word 8 08-30-2015 01:08 PM
20 day gap indicator Task Indicator - All predecessors complete true/false, y/n jdove78 Project 2 10-10-2012 05:53 PM
20 day gap indicator On-screen indicator for overtype mode? carrfamily@mindspring.com Word 3 04-29-2011 01:56 PM
Next Page Indicator mkstreet PowerPoint 0 12-08-2010 11:36 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:30 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft