actuals vs estimates
 
Join Date: Nov 2010
Posts: 13
projectman is on a distinguished road
Default

Kimberly

I tried your suggestion and I could not get the actuals to agree with what I was putting in.
the example I used

I have the calandar set to a 6 hour work day.
baseline start 11/01/10 baseline finish 11/03/10 baseline work 18
actual start 11/01/10 act finish 11/02/10 actual hours 9

if I enter the act start of 11/01/10 and the act finish of 11/02/10 and the act work at 9, the act work changes to 12 and the % comp is 100. if I change the act work back to 9, the act finish goes to NA and the % comp goes to 75.
I am beginning to think that project can't do estimates verus actual tracking.
Reply With Quote
 



Other Forums: Access Forums

All times are GMT -7. The time now is 01:04 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft