Thread: [Solved] actuals vs estimates
View Single Post
 
Old 11-11-2010, 03:32 PM
Kimberly Kimberly is offline Windows 7 Office 2010 (Version 14.0)
Expert
 
Join Date: May 2010
Posts: 517
Kimberly is on a distinguished road
Default

Don't give up already! This is not a typical use of Project, and it is taking me some time to figure out what you are doing, but I do believe it will work fine. I think you do not use the difference between work and duration, but for your purposes they are the same thing.

Try this:

Change the fields.
Get rid of all fields that contain the word "Work"
Instead add fields so they're in this order:
Name, Baseline Start, Baseline Finish, Baseline Duration, Actual Start, Actual Duration, % Comp, Actual Finish

See if you can enter the baselines (you can enter the Baseline Dur as 18h) and then the ActualStart and then ActualDuration (9h) and project will calculate the rest.
Reply With Quote