Old 11-11-2010, 07:42 AM
projectman projectman is offline actuals vs estimates Windows XP actuals vs estimates Office 2003
Novice
actuals vs estimates
 
Join Date: Nov 2010
Posts: 13
projectman is on a distinguished road
Default

Kimberly

thanks for working with me on this. I still am not getting this

I have 6 fields
id est-start-date est-end-date est-hrs act-start-date act-end-date act-hrs

I just want to compare the est fields against the act fields. it didn't sound that difficult when I started this but now I am not so sure.

I get tickets every day. I will add tickets to the project every day. I need a way to save the estimate data so i does not get overlaid with the actual data.
Reply With Quote
 



Other Forums: Access Forums

All times are GMT -7. The time now is 04:16 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft