Ressources on Parallel Tasks
 
Join Date: Jun 2023
Posts: 5
muellerschneider is on a distinguished road
Default Ressources on Parallel Tasks

Hello Guys,




i have a Project, where I have two Tasks. One lasts one year and has a work duration of one full time equivalent(FTE), the other one 2 years but only need half FTE. Therefore one FTE would be enough to finish both tasks after two years. I want to enter into project for the first task 1 FTE over the full duration, and 50% FTE over two years. how can I make Project to automatically plan the FTE for 100% on the second task?


Thank you
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Tasks - Ressources report ? cioknarf Project 0 12-14-2021 03:17 AM
Check amount of free ressources Albert HAFENSCHER Project 0 06-28-2017 12:51 AM
Ressources on Parallel Tasks Parallel animation schemes Chuker PowerPoint 2 03-04-2016 12:44 PM
Ressources on Parallel Tasks How to create "parallel" tasks? A.S. Project 4 10-29-2015 03:06 PM
Ressources on Parallel Tasks Auto-level resources for parallel tasks with fixed work cineasta Project 5 11-21-2013 01:03 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:04 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft