Hi, let me explain my problem with an example
I have a task which takes 5 weeks and 500% resources to be done. How can i set this task to take 10 weeks using 300% resource in first 5 weeks and then 200% resource in next 5 weeks? I don't want to split this into 2 tasks (ie. part 1, part 2) Thank you in advance |
Tags |
resource allocation |