![]() |
#1
|
|||
|
|||
![]()
hi everyone, i am new to the forum.
I have a question (maybe obvious to you!) if for a task I have 100 hours available but for this project I can dedicate only 20% of the resource how do I get the correct task duration? |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Physical % Complete and Task Duration | ChuckM | Project | 3 | 02-09-2014 09:21 AM |
![]() |
DarlaWeber | Project | 1 | 01-31-2014 02:30 PM |
Floating task duration | dbsoccer | Project | 5 | 10-31-2013 09:10 AM |
![]() |
branchi | Project | 1 | 08-15-2013 06:03 AM |
Task duration between 2 fixed milestones | cettolox | Project | 3 | 01-24-2012 06:33 AM |