#2
|
||||
|
||||
![]()
Make your Lorry Hire Task a Hammock.
To create a hammock, copy the start date of the first Task that uses the equipment and use Paste Special >> Paste Link, to paste in the start date field of the Lorry Hire Task. Similarly, copy the finish date of the last Task that uses the equipment and use Paste Special >> Paste Link, to paste in the finish date field of the Lorry Hire Task. Your Lorry Hire Task should now be dynamically linked to equipment use and a change in equipment use Tasks duration will also change Lorry Hire duration. You can confirm Lorry Hire is dynamically linked as there should be a small black triangle at the bottom right corner of the Start & Finish dates. Planners' Place |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Competing a task in Outlook does not automtically complete the linked task in OneNote | OneGoat | OneNote | 0 | 06-22-2017 05:55 AM |
How to make a task adjust its end date depending on another task? (Newbie) | ravl13 | Project | 3 | 07-27-2014 06:10 PM |
![]() |
DarlaWeber | Project | 1 | 01-31-2014 02:30 PM |
![]() |
branchi | Project | 1 | 08-15-2013 06:03 AM |
![]() |
Antares | Project | 1 | 12-14-2011 09:19 AM |