Lou C Lou C is offline How to adjust Project Duration for Summer and Winter Hours - based on number of hours per day Windows 10 How to adjust Project Duration for Summer and Winter Hours - based on number of hours per day Office 2019
Novice
How to adjust Project Duration for Summer and Winter Hours - based on number of hours per day
 
Join Date: Oct 2021
Posts: 2
Lou C is on a distinguished road
Default Project Durations

Hi Jerome

Thanks so much for your reply. I suspected that. I might try your suggestion but might be a step too far for the user who needs this.

Louise
Reply With Quote
 

Tags
adjust duration, summer calendar, winter calendar



Similar Threads
Thread Thread Starter Forum Replies Last Post
adding up hours as numbers doesnt match hours as time format DBenz Excel 12 11-05-2018 02:53 PM
How to adjust Project Duration for Summer and Winter Hours - based on number of hours per day Duration & Work Hours Not Close fkistner Project 1 10-31-2015 11:51 AM
How to adjust Project Duration for Summer and Winter Hours - based on number of hours per day Resource not getting enough hours allocated to them, therefore extending duration joday48 Project 1 08-01-2014 08:54 AM
How to adjust Project Duration for Summer and Winter Hours - based on number of hours per day Project Hours Mav Project 4 03-07-2014 04:47 PM
MS Project-timescale in hours John Franklin Project 5 10-30-2013 08:41 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:35 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft