Resource not getting enough hours allocated to them, therefore extending duration
Hi
I have a base calendar of 8 hours per day. Example: I have Bob who has a resource calendar of 6 hours per day. Joe has a resource calendar of 4 hours per day. I assign them both to a 40 hour task as follows: Bob at 80%, and Joe at 20%. Why is the duration calculating 7.38 days? Additionally when I go into the resource usage view, it shows the following that joe is only being allocated 0.8 work per day. This is extending the duration. Further more the dates are 31/07/14 - 13/08/14. This is not 7.38 days??!! Please help! Thanks jo |
#2
|
|||
|
|||
You have assigned Joe at 20% of 4 hours per day (his calendar) which is .8 hours per day. You have assigned Bob at 80% of 6 hours per day (his calendar) which is 4.8 hours per day. If you want Bob to work 6 hours per day and Joe to work 4 hours per day, assign them at 100%.
I get 6.5 days calculated with a task start of July 31 at 8:00 am and a finish of August 13 at 12:00 pm. Bob is working 32 hours (80% of 40) and finishes at 12:00 pm on August 8 - and Joe is work 8 hours (20% of 40) and finishes on August 13 at 12:00 pm. In File, Options what is your definition of "hours per day"". |
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Gantt bar text labels - possible to put resource hours against the bars? | mtbtomo | Project | 5 | 05-14-2014 01:18 PM |
Levelling resource's units to calculate duration task | codeghi | Project | 10 | 03-01-2014 08:13 AM |
Mid-Task resource scheduled 0 hours increasing task duration needlessly | DarlaWeber | Project | 1 | 01-31-2014 02:30 PM |
Over-allocated resource - resource holiday | scott.hannaford | Project | 1 | 10-21-2013 05:32 AM |
Over allocated with only 1300 hours in a year?!!! | msproject2010 | Project | 1 | 08-01-2011 04:29 AM |