Your "Duration" field calculates the difference between Start & Finish dates, while your "Total Duration" field sums up the duration of sub-tasks under a Summary task.
Did you inherit the schedule? Just curious as to why you would add a field to the schedule if you don't know what it does. BTW, I want to believe your "Total Duration" is a custom field and not a default Microsoft Project field as it is not listed in the list of duration fields. Duration fields - Project Last edited by ProjectPlanner; 07-17-2021 at 09:27 PM. Reason: edited for clarity |
|
![]() |
||||