![]() |
#1
|
|||
|
|||
![]() I am using MS Project Standard 2003 SP3 and have experience instances in which the automatic calculation of work effort fails to work when I change duration. Has anyone else experienced this and know why it happens and how to prevent it? I created by project schedule with if effort driven and began to modify some resources. As expected, the modification to the resources updates the durations for the tasks, so I change duration back (since project is fixed duration on tasks) and the work updates as expected, so I proceed down the remaining 600 lines. Upon reviewing the resource usage I notice some are way off and find that not all the work efforts updated. ![]() Needless to say I would rather not go through all 600+ lines again in the future and would prefer to not have to check every line item I change to ensure project calculates as expected. I would very much appreciate any feedback or words of advice. Thanks John |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
stats | Project | 1 | 04-11-2010 04:12 PM |
custom formula for duration | ericfons | Project | 0 | 03-23-2010 01:18 PM |
Secondary IP address Outlook Fail-over | danish.mustafa | Outlook | 0 | 03-01-2010 01:32 AM |
Shortcuts Fail | sussertown | Outlook | 0 | 02-16-2009 06:38 PM |
![]() |
bgane | Project | 1 | 03-20-2006 06:36 AM |