![]() |
|
#1
|
|||
|
|||
|
Hi, I have here two sets of a project schedule. The schedules are exactly the same however, one have the Task 1 constraint as "As soon as possible" while the other one set as "Start no earlier than". The duration is the same for both file but I am confused on why MS Project would give me two different resource leveling just because of the constraint on my first task. Any idea why? Thanks. |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
Problem leveling
|
Charli | Project | 7 | 02-14-2017 04:54 AM |
Leveling Resources Help!
|
Mthomas88 | Project | 1 | 09-25-2015 08:25 AM |
problem with leveling
|
r77 | Project | 5 | 09-17-2015 05:04 AM |
Certain Resources Not Leveling
|
PDX-ADM-TRM01 | Project | 1 | 04-27-2015 03:45 PM |
| Question about leveling a project..... | sssb2000 | Project | 3 | 02-05-2015 12:11 PM |