Hi,
I have here two sets of a project schedule. The schedules are exactly the same however, one have the Task 1 constraint as "As soon as possible" while the other one set as "Start no earlier than". The duration is the same for both file but I am confused on why MS Project would give me two different resource leveling just because of the constraint on my first task. Any idea why? Thanks. |
|
![]() |
||||