Same Schedule, but different leveling
 
Join Date: Sep 2017
Posts: 1
stahleen17 is on a distinguished road
Default Same Schedule, but different leveling


Hi,

I have here two sets of a project schedule. The schedules are exactly the same however, one have the Task 1 constraint as "As soon as possible" while the other one set as "Start no earlier than". The duration is the same for both file but I am confused on why MS Project would give me two different resource leveling just because of the constraint on my first task. Any idea why? Thanks.
Attached Files
File Type: mpp Sample B.mpp (273.0 KB, 9 views)
File Type: mpp Sample A.mpp (272.5 KB, 9 views)
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Same Schedule, but different leveling Problem leveling Charli Project 7 02-14-2017 04:54 AM
Same Schedule, but different leveling Leveling Resources Help! Mthomas88 Project 1 09-25-2015 08:25 AM
Same Schedule, but different leveling problem with leveling r77 Project 5 09-17-2015 05:04 AM
Same Schedule, but different leveling Certain Resources Not Leveling PDX-ADM-TRM01 Project 1 04-27-2015 03:45 PM
Question about leveling a project..... sssb2000 Project 3 02-05-2015 12:11 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:14 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft