#2
|
|||
|
|||
|
I'm afraid the Task Information window is not configurable by users. If you are using Project 2016, you can use the Task Drivers to determine which predecessor is driving the task in question. You may also find using the Task Form in the lower portion of your window saves a lot of double clicking. It can be formatted to show predecessor and successors.
|
|
|