Hey Tony and thanks for that link. Not really sure it is answering my question though since as I understood the info was illustrating ongoing tasks with a later completion date.
In my case a milestone, set as 100% complete still creates a late warning of the summary task it resides within. The other tasks within the same summary task is not due to start in another 20 work days. Attached is a SS with the column Status added just to illustrate that there are not any planned work going on. |
|
![]() |
||||