Do you have a gap in the subtasks? So, for example, you have tasks that are complete and then a gap with tasks in the future? Still not sure why things are incorrect. Are there any tasks with incomplete work in the past? Add the status line to the Gantt chart - is everything to the left marked complete and any remaining work moved to the right of the status line?