#1
|
|||
|
|||
![]() Hi, i have planed a project. Now i will assign some resources(Workers) to the specifics process. With the assign i have some question and i hope u can help me... I have a process Duration 100 days, Work 100h If i put 1 resource on this process ms project shared the whole work over this 100 days. Put i want that my resource works the first 5 days 40h then in the middle 20h and the last 5 days 40h. How i can tell ms project when the resource must done his works? i hope u understanding what i mean ;-) thx... |
|
![]() |
||||