Originally Posted by flownfluid View Post
Hi,

i have planed a project. Now i will assign some resources(Workers) to the specifics process.

With the assign i have some question and i hope u can help me...

I have a process Duration 100 days, Work 100h
If i put 1 resource on this process ms project shared the whole work over this 100 days.
Put i want that my resource works the first 5 days 40h then in the middle 20h and the last 5 days 40h.
How i can tell ms project when the resource must done his works?

i hope u understanding what i mean ;-)

thx...
You can edit the spread of work in the Resource Usage view.