Planing Resources
Hi,
i have planed a project. Now i will assign some resources(Workers) to the specifics process.
With the assign i have some question and i hope u can help me...
I have a process Duration 100 days, Work 100h
If i put 1 resource on this process ms project shared the whole work over this 100 days.
Put i want that my resource works the first 5 days 40h then in the middle 20h and the last 5 days 40h.
How i can tell ms project when the resource must done his works?
i hope u understanding what i mean ;-)
thx...
|