Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #2  
Old 01-11-2017, 06:38 PM
JulieS JulieS is offline physical % complete Windows 7 64bit physical % complete Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hi Andy,

Unless the work is progressing at an even pace throughout the entire project, the % complete - which is a duration measure - will not equal the % work complete. For example in the beginning of a project you may not have as many hours expended in each month as you may have later in the project when more resources join. So, you may have progressed 2% of the total duration, but because of backloaded resources, you have not consumed 2% of the total work. Look a the task usage view, add work to the timescaled portion zoom out and look at your work load per month.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
physical % complete How to show planned% complete and actual% complete on the (Project Overview) dashboard report? zislam14 Project 3 12-17-2015 03:03 PM
physical % complete physical complete %, regular work, vs % complete ketanco Project 1 06-16-2014 11:08 AM
Physical % Complete and Task Duration ChuckM Project 3 02-09-2014 09:21 AM
physical % complete project for projected vs physical theWizardAKQ Project 3 01-24-2014 06:16 AM
physical % complete complete % and physical complete % ketanco Project 3 05-25-2012 08:19 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:05 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft