![]() |
|
#2
|
|||
|
|||
|
Hi Andy,
Unless the work is progressing at an even pace throughout the entire project, the % complete - which is a duration measure - will not equal the % work complete. For example in the beginning of a project you may not have as many hours expended in each month as you may have later in the project when more resources join. So, you may have progressed 2% of the total duration, but because of backloaded resources, you have not consumed 2% of the total work. Look a the task usage view, add work to the timescaled portion zoom out and look at your work load per month. |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
How to show planned% complete and actual% complete on the (Project Overview) dashboard report?
|
zislam14 | Project | 3 | 12-17-2015 03:03 PM |
physical complete %, regular work, vs % complete
|
ketanco | Project | 1 | 06-16-2014 11:08 AM |
| Physical % Complete and Task Duration | ChuckM | Project | 3 | 02-09-2014 09:21 AM |
project for projected vs physical
|
theWizardAKQ | Project | 3 | 01-24-2014 06:16 AM |
complete % and physical complete %
|
ketanco | Project | 3 | 05-25-2012 08:19 AM |