#2
|
|||
|
|||
|
I have no idea what "desired" result you are looking for. I have watched the first 3 minutes of the video and by following the steps get the exact same answer the demonstration did.
Depending upon how you assign the resources, the 24 hours of work may be split evenly (8 hours each). In the video R1 and R2 are scheduled for 9.6 hours and R3 is scheduled for 4.8 hours. If you want it to finish more quickly - change the work for R1 and R2 to 11 hours and change the work for R3 to 2 hours. It now finishes Friday at 3:00 pm. The calculation by project is not incorrect - it is based upon 24 hours of work split among a total of 125% units. R1 is 40% of the total of 125% and 40% of 24 is 9,6. The same is true with R2 - hence the assignment of 9.6 hours of work. Project does not pay attention to the idea that R3 only works on Wednesday (in this scenario) - so it still assigns 20% of the 24 hours of work - or 4.8 hours. |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| How to make a task adjust its end date depending on another task? (Newbie) | ravl13 | Project | 3 | 07-27-2014 06:10 PM |
Passed due task end date
|
tcalderini | Project | 1 | 09-19-2013 04:56 AM |
macro for reflecting objects along all slides
|
samifox | PowerPoint | 3 | 05-05-2012 01:58 AM |
| Task with Start date but no Due date? | bplat | Outlook | 0 | 01-12-2012 08:10 AM |
| Task type relationships not acting as expected | Rkramkowski | Project | 0 | 12-08-2005 10:40 AM |