You need to give a bit more information, I am afraid.
the critical path is not something that you make, it is the set of tasks that have no float on them, or to put it another way, if any of them slip by any time, the finish date will change.
Generally there will be always be a critical path. the main reasons for not seeing one are constrained dates (these will skew the programme), or set start and finish dates that are further apart than the duration of the programmed items. In this case, generally you would add a float bar- this links from any task that does not have a successor (something happening after it) and links to the finish date. The duration of this can be set so that it takes up all the slack in the programme, and this will then allow the critical path to be shown.

If you need more help, then an example would be ideal, or a bit more explanation as to the exact problem.

hope this helps.
Reply With Quote
 

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Critical path not displayed on Gantt Chart JPolise Project 12 05-19-2021 11:50 AM
Critical Path workload forecasts Planner18 Project 1 07-01-2015 01:34 PM
Critical Path Length ketanco Project 5 03-15-2013 01:12 PM
critical path starting in future ketanco Project 5 07-27-2012 02:50 PM
Critical path Critical Path w/ 2 Calendars AndreT Project 6 07-27-2011 11:22 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:10 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft