The meeting task is the predecessor. If the date of the meeting changes the successor tasks schedules will also change.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Need to schedule a project based on end date Schedule deviation based on teams csokosdama Project 1 03-03-2015 08:24 AM
what to put in to schedule for dealing with overall finish date ketanco Project 7 10-30-2014 02:25 PM
Need to schedule a project based on end date Error occurred, when I went to open a MS Project schedule. HermannBaumgartner Project 1 10-29-2014 10:58 AM
I can't figure out how to get Project 2010 to automatically rebalance my schedule jackofnothing Project 0 10-23-2011 04:04 PM
Powerpoint project schedule L J Keane Project 0 09-14-2010 01:24 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:38 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft