Need to schedule a project based on end date
View Single Post
10-03-2016, 07:00 AM
JulieS
Windows 7 64bit
Office 2013
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
You can schedule a project from a finish date using Project Information. Select Schedule from: and select finish date.
If it is just one task that needs to be scheduled 6 weeks before - use a Finish to start link with a 6 week lead.