JulieS JulieS is offline Need to schedule a project based on end date Windows 7 64bit Need to schedule a project based on end date Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You can schedule a project from a finish date using Project Information. Select Schedule from: and select finish date.

If it is just one task that needs to be scheduled 6 weeks before - use a Finish to start link with a 6 week lead.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Need to schedule a project based on end date Schedule deviation based on teams csokosdama Project 1 03-03-2015 08:24 AM
what to put in to schedule for dealing with overall finish date ketanco Project 7 10-30-2014 02:25 PM
Need to schedule a project based on end date Error occurred, when I went to open a MS Project schedule. HermannBaumgartner Project 1 10-29-2014 10:58 AM
I can't figure out how to get Project 2010 to automatically rebalance my schedule jackofnothing Project 0 10-23-2011 04:04 PM
Powerpoint project schedule L J Keane Project 0 09-14-2010 01:24 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:31 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft