Rollup of mulitple sub tasks and non-working days
I have a basic project set up with multiple levels of sub tasks under one summary tasks. (see photo attached). The thing I cant figure out is this:
using 168004 (green summary task) as an example, I have one project (a 91 day) that started and finished in January 2016. Another project (pmi support) started in july. How can I make the green summary task ONLY show the total days I actually worked, and not the total span from the start of the first one to the end of the second one.
|