View Single Post
 
Old 09-22-2016, 10:03 AM
jkdiesel jkdiesel is offline Windows 7 64bit Office 2013
Novice
 
Join Date: May 2016
Posts: 11
jkdiesel is on a distinguished road
Default Rollup of mulitple sub tasks and non-working days

I have a basic project set up with multiple levels of sub tasks under one summary tasks. (see photo attached). The thing I cant figure out is this:

using 168004 (green summary task) as an example, I have one project (a 91 day) that started and finished in January 2016. Another project (pmi support) started in july. How can I make the green summary task ONLY show the total days I actually worked, and not the total span from the start of the first one to the end of the second one.
Attached Images
File Type: png untitled.png (49.5 KB, 14 views)
Reply With Quote