Guloluseus Guloluseus is offline Rollup of mulitple sub tasks and non-working days Windows 7 64bit Rollup of mulitple sub tasks and non-working days Office 2010 32bit
Competent Performer
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default


the simple answer is that if you want to keep your current programme, you cannot. A summary bar is just that;a summary. It starts on the first day under it and finishes on the last one. Any gaps or non working time dont matter.

If you are happy to change the layout, you can make another summary task at the same level as the 168004 one and give it a new name. this would then separate out the 2 projects as separate. as far as I know, thats pretty much te only options.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
conflicting tasks with exception days damokaa Project 1 04-05-2016 06:11 AM
Rollup of mulitple sub tasks and non-working days reminder for every 15 working days araamuthan Outlook 1 03-25-2015 11:49 PM
reminder for every 15 working days araamuthan Excel 0 03-25-2015 06:49 AM
Rollup Summary Tasks to Project Summary Task shep555 Project 1 05-24-2014 12:28 PM
Rollup of mulitple sub tasks and non-working days Non-Working Days on Gantt JayTT Project 1 01-28-2011 05:42 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:12 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft