#1
|
|||
|
|||
![]()
I'm not sure what's going on with Project, but here's what's happening (hoping you guys can help me)
When I add a task, and then try to add the start and finish dates, Project keeps setting my dates to the same day...with a duration of 1 day. For example, I want to enter the following and have project calculate the duration: Task Duration Start Finish Test A (calculated) 9/1/2016 9/5/2016 But what happens is, I enter the start date, then the finish date, and Project sets them both to the same date with a duration of 1 Day. Do I have a global setting wrong or something? |
#2
|
|||
|
|||
![]()
If you want to manually enter task start and finish dates, you'll need to work with manually scheduled tasks. Then you should be able to manually type start and finish dates.
|
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
Rowey | Project | 5 | 05-01-2015 07:22 AM |
![]() |
ketanco | Project | 2 | 09-17-2014 05:21 PM |
start and finish dates exceeding duration | joday48 | Project | 0 | 06-27-2012 04:55 AM |
![]() |
ketanco | Project | 1 | 12-14-2011 09:06 AM |
![]() |
benson.wallace | Project | 2 | 12-05-2010 07:22 AM |