Project forcing start and finish dates to be the same day
View Single Post
09-28-2016, 11:37 AM
JulieS
Windows 7 64bit
Office 2013
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
If you want to manually enter task start and finish dates, you'll need to work with manually scheduled tasks. Then you should be able to manually type start and finish dates.