![]() |
|
#2
|
|||
|
|||
|
If you want to manually enter task start and finish dates, you'll need to work with manually scheduled tasks. Then you should be able to manually type start and finish dates.
|
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
Finish to Start Tasks dates incorrect
|
Rowey | Project | 5 | 05-01-2015 07:22 AM |
Milestones with different start and finish dates
|
ketanco | Project | 2 | 09-17-2014 05:21 PM |
| start and finish dates exceeding duration | joday48 | Project | 0 | 06-27-2012 04:55 AM |
duration vs actual start and finish dates
|
ketanco | Project | 1 | 12-14-2011 09:06 AM |
displaying start and finish times as absolute numbers instead of dates
|
benson.wallace | Project | 2 | 12-05-2010 07:22 AM |