Start with the Budget Work Visual Report
Select Level of usage data = Weeks. Click View to create the report and export the data to Excel. Click the Assignment usage tab in the Excel spreadsheet to see the Pivot table In the Pivot Table field list, click Resources to add Resources to the list. Drag Tasks from the Filters area into the Rows area after Resources Right click on one of the tasks and select Show Properties in Report. Select Scheduled Start and Scheduled Finish to show the dates of the task Drag weekly calendar to Columns Uncheck Actual work, Baseline Work, and Budget work to see just Work. Hide columns as needed. You can also get very close to the Who Does What report by printing the Resource usage view. As needed add the Start and Finish dates to see when the work occurs. |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
fkistner | Project | 1 | 10-31-2015 11:51 AM |
![]() |
Cameronk | Project | 1 | 05-14-2015 02:29 PM |
![]() |
cuseman03 | Project | 5 | 05-14-2015 02:19 PM |
Work not changing duration | benoldays | Project | 0 | 02-14-2011 08:21 PM |
Duration changes fail to update work effort | Panteledes | Project | 6 | 05-25-2010 02:27 PM |