Hello Julie,
my problem is this: A tasks starts on Oktober 20th with a duration of 30 days. So part of the task will be done in Oktober, the rest in November. I need to report how many hours (duration and work) are for a single ressource in a specific week and month. It seems to me, that the current reports do not represent this (tabluar and graphical (visual) Reports. I that true? if so, I could set up a filter for each week and month and get the result from MS Project and export the stuff to excel - and continue there. I am really missing the report (2010): Who is what doing when. Regards Bruno |
|
![]() |
||||