Hello Julie,

my problem is this: A tasks starts on Oktober 20th with a duration of 30 days. So part of the task will be done in Oktober, the rest in November.

I need to report how many hours (duration and work) are for a single ressource in a specific week and month.

It seems to me, that the current reports do not represent this (tabluar and graphical (visual) Reports.

I that true?

if so, I could set up a filter for each week and month and get the result from MS Project and export the stuff to excel - and continue there.

I am really missing the report (2010): Who is what doing when.

Regards
Bruno