Hello,
I have a project planning based on a resource pool. I assign the non-working days in the calendar of resources on the "Resource.mpp" file. After this modification, I see a correct planning adjusting in MP2010 that takes into account of non-working days, while with MP2013 I don't see it! I have attached a file wherewith you could verified it: if I assign non working days for "Luke" resource (13-16 June), the "congress" task in "Task1" file is not re-allocated in MP2013. I ask you if there is a particular setting in MP2013 version that could resolve the problem. Bye |
|
![]() |
||||