Need help understanding critical path and feedback on programme.
 
Join Date: Mar 2014
Location: Zambia
Posts: 61
c991257 is on a distinguished road
Default Need help understanding critical path and feedback on programme.

Hi.



I've made a programme for a one of our projects and have changed the traditional way that the programme is made.

We build roads and tend to use links to control the order in which the roads are built, however that never works well. I've changed that by not linking individual roads and used priorities and resources to control the order in which each road is built. I think that makes much more sense, however the consequence seems to be that the critical path is now decided by a single road (that last one), and if I set MS Project to calculate multiple critical then almost everything becomes critical.

I would like opinions on whether or not the way I've done the programme is "correct" but also comments on the critical path issue.

I had to zip the programme (MS Project 2010) to upload it.

/Møller
Attached Files
File Type: zip 306, ARZ, Programme, 2016-04-12 -3.zip (521.0 KB, 13 views)
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Critical Path workload forecasts Planner18 Project 1 07-01-2015 01:34 PM
Critical Path Length ketanco Project 5 03-15-2013 01:12 PM
Need help understanding critical path and feedback on programme. analysing contractor schedule for critical path ketanco Project 1 02-07-2013 06:49 AM
critical path starting in future ketanco Project 5 07-27-2012 02:50 PM
Need help understanding critical path and feedback on programme. Critical Path w/ 2 Calendars AndreT Project 6 07-27-2011 11:22 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:40 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft