Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 03-24-2016, 05:05 AM
rtuttle rtuttle is offline Start & Finish Date/Time Windows 7 64bit Start & Finish Date/Time Office 2013
Novice
Start & Finish Date/Time
 
Join Date: Mar 2016
Location: Greenville SC
Posts: 11
rtuttle is on a distinguished road
Default Start & Finish Date/Time


How do you change a template so the date/time are the same for start and finish when no tasks are entered... If I start a new project and check the "Show project summary task" the start and finish date/times are the same and finish time changes as tasks are added... MY (inherited) template shows...(example) start date/time as 4/12/16 8:00am and finish date/time 4/13/16 8:30am and no tasks are entered.. How can I correct this so the finish date/time grows as tasks are added...
Reply With Quote
  #2  
Old 03-24-2016, 06:22 AM
JulieS JulieS is offline Start & Finish Date/Time Windows 7 64bit Start & Finish Date/Time Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

My guess is the Project start time was not updated when the calendar was changed to start at 8:30. What is the start time in the calendar? (Change working time). What is the default start time (File > Options, Schedule).
Reply With Quote
  #3  
Old 03-24-2016, 06:49 AM
rtuttle rtuttle is offline Start & Finish Date/Time Windows 7 64bit Start & Finish Date/Time Office 2013
Novice
Start & Finish Date/Time
 
Join Date: Mar 2016
Location: Greenville SC
Posts: 11
rtuttle is on a distinguished road
Default

Wow another issue.. Gantt Chart start time shows 8:00am..

File> Option: Schedule indicate 6:00am start time..

Change Work Time: default is 6:00am

I would start a new template, the date and times all align as they should, but the resource list is really big and I'm not sure how to move all of that info or reenter it.
Reply With Quote
  #4  
Old 03-26-2016, 06:42 PM
JulieS JulieS is offline Start & Finish Date/Time Windows 7 64bit Start & Finish Date/Time Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

The setting are for the project - not each resources. But the calendar and calendar options must match. If the resources are all set to work against the base calendar = project calendar - you should be all set.
Reply With Quote
  #5  
Old 03-30-2016, 03:56 AM
rtuttle rtuttle is offline Start & Finish Date/Time Windows 7 64bit Start & Finish Date/Time Office 2013
Novice
Start & Finish Date/Time
 
Join Date: Mar 2016
Location: Greenville SC
Posts: 11
rtuttle is on a distinguished road
Default

I matched all the dates and times and deleted all the tasks... it worked.
But the "Project information" Title, that shows up at the top of the Gantt chart
still shows the "finish" date/time as 24.5 hours till finished..

But once I enter a start task and time, the Project info title reflects the latest "finish" time...
It works as it should and looks correct, but the set up is not correct, and that kinda bothers me..
Reply With Quote
  #6  
Old 04-05-2016, 06:13 AM
JulieS JulieS is offline Start & Finish Date/Time Windows 7 64bit Start & Finish Date/Time Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

What is the duration of the Project Summary task - line 0. Without any tasks the duration should be zero and start date/time = finish date/time
Reply With Quote
  #7  
Old 04-12-2016, 04:11 AM
rtuttle rtuttle is offline Start & Finish Date/Time Windows 7 64bit Start & Finish Date/Time Office 2013
Novice
Start & Finish Date/Time
 
Join Date: Mar 2016
Location: Greenville SC
Posts: 11
rtuttle is on a distinguished road
Default

I found the issue about about the dates and start time.. (in my case, anyway)

There were "cleared" tasks NOT "deleted".. and once I deleted the tasks, and entered new tasks and duration the dates and time fell into place...
Reply With Quote
  #8  
Old 04-14-2016, 05:53 AM
JulieS JulieS is offline Start & Finish Date/Time Windows 7 64bit Start & Finish Date/Time Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Not sure what 'cleared' tasks means - but they must be deleted for the summary duration to = 0.
Reply With Quote
  #9  
Old 04-14-2016, 11:08 AM
rtuttle rtuttle is offline Start & Finish Date/Time Windows 7 64bit Start & Finish Date/Time Office 2013
Novice
Start & Finish Date/Time
 
Join Date: Mar 2016
Location: Greenville SC
Posts: 11
rtuttle is on a distinguished road
Default

I "cleared contents" in the cells and still had issues with start/finish time when I had "show project summary task" in the Zero line...

I highlighted the cells again and used "clear contents".... Summary dates still the same....Then used "delete tasks".. and the Summary was showing correct start/finish...

I have started a new project template and it is working.. Just need to get the resources entered
Reply With Quote
  #10  
Old 04-15-2016, 06:18 AM
JulieS JulieS is offline Start & Finish Date/Time Windows 7 64bit Start & Finish Date/Time Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Ah, thanks for the clarification.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Start & Finish Date/Time How to set a filter for tasks that will start & finish in two weeks? zislam14 Project 1 12-17-2015 03:58 PM
Start & Finish Date/Time Milestones with different start and finish dates ketanco Project 2 09-17-2014 05:21 PM
flag to indicate finish date does not equal baseline finish date TCB Project 3 08-06-2014 02:49 PM
Start & Finish Date/Time duration vs actual start and finish dates ketanco Project 1 12-14-2011 09:06 AM
MS Project able to import actual start and or actual finish date from Excel? mhacker Project 0 04-26-2010 11:29 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:50 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft