![]() |
|
#1
|
|||
|
|||
|
I use a separate text column to indicate tasks assigned to various project managers. There are multiple sub-projects within the project. I've created a filter that shows tasks assigned per that column which then allows me to see remaining work, but I cannot find an easy way to sum the remaining work column. I currently copy and paste it into excel, but I'd like to do it all within MSP. Does anyone have a method for this? |
| Tags |
| sum |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| formula to work from data column | masterdineen | Excel | 16 | 08-09-2012 07:52 AM |
| Change Resource Time vs. Duration when Updating Work column | lylel | Project | 3 | 07-23-2012 06:09 PM |
| Displaying Work Week instead of date in a column. | whitney07 | Project | 1 | 07-05-2012 02:27 PM |
definition of work column
|
ketanco | Project | 9 | 05-31-2012 05:15 PM |
adjusting remaining work per status date
|
ketanco | Project | 1 | 03-16-2012 06:02 AM |