Jacke Jacke is offline New project Windows 7 64bit New project Office 2010 64bit
Novice
New project
 
Join Date: Feb 2016
Posts: 4
Jacke is on a distinguished road
Default


Thank You for information
Please look now I make auto scheduled, but everything start in the same time and worker is overload.
Capture2.JPG
It is possible to make schedule base on pririty and date before which should be done ? without connetion beetween tasks ?
scheduled3.mpp
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
project server 2007 - project checkin failed at 37% marcoheras Project 1 07-01-2015 01:42 PM
Example for using Ms Project in construction project safaa Project 1 11-08-2012 05:54 AM
Connectivity issue of Project Professional with Project Server kashif Project 0 03-27-2009 06:37 AM
Error 9571 when opening Project Server from Project Pro mona Project 0 04-24-2007 07:50 AM
Different % complete in Project Center & View a Project mikaelbelchior Project 1 01-25-2006 12:56 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:09 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft