Thank You for Your help its important for me.
Please look for picture, why working time is 361hours, if task is only 10 meeting with duration time 1hrs For me it schould be 10hrs
Capture.JPG
I try make new plan with autoscheduled and fill duration time but everthing is planned on one day. Ther isn't overload for worker1. Task 2 should start 22.02.16 13:00 and end in 23.02.16
scheduled2.mpp