Hello everyone
I try use Microsoft project and I start check how it's works.
I make very simple project few tasks for one person, every time I have similar problem that. Resource/ worker have only planned one task in day even duration is 6hours and working day is 8. Otherwise resource have ex. 14 hours of work for day. Standrd day is from monday to friday from 7am to 3pm
For me the most important think is auto planning based on priority, duration time and deadline. Only if priority another task is bigger than deadline for task with lower priority should be moved
In the end I want make work plan for 5 people
1. It is possible to do in MProject ?
2. I inlcude in attachement example of file. Can somebody help me and make usefull schedulded from this file ?
Projekt2.mpp