#1
|
|||
|
|||
![]()
If there is a relationship between tasks (I can't start task 2 until task 1 is complete) then link them. I opened your schedule - it is apparently linked to another schedule which you didn't include.
The tasks are still all manually scheduled. Regarding the above - all of the subtasks are manually scheduled. Do no assign the resource to the summary task - he/she should be assigned to each meeting. |
#2
|
|||
|
|||
![]()
Thank You for information
Please look now I make auto scheduled, but everything start in the same time and worker is overload. Capture2.JPG It is possible to make schedule base on pririty and date before which should be done ? without connetion beetween tasks ? scheduled3.mpp |
![]() |
Thread Tools | |
Display Modes | |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
project server 2007 - project checkin failed at 37% | marcoheras | Project | 1 | 07-01-2015 01:42 PM |
Example for using Ms Project in construction project | safaa | Project | 1 | 11-08-2012 05:54 AM |
Connectivity issue of Project Professional with Project Server | kashif | Project | 0 | 03-27-2009 06:37 AM |
Error 9571 when opening Project Server from Project Pro | mona | Project | 0 | 04-24-2007 07:50 AM |
Different % complete in Project Center & View a Project | mikaelbelchior | Project | 1 | 01-25-2006 12:56 AM |