#4
|
|||
|
|||
![]()
If there is a relationship between tasks (I can't start task 2 until task 1 is complete) then link them. I opened your schedule - it is apparently linked to another schedule which you didn't include.
The tasks are still all manually scheduled. Regarding the above - all of the subtasks are manually scheduled. Do no assign the resource to the summary task - he/she should be assigned to each meeting. |
|
![]() |
||||