Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #4  
Old 02-25-2016, 09:25 AM
JulieS JulieS is offline New project Windows 7 64bit New project Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

If there is a relationship between tasks (I can't start task 2 until task 1 is complete) then link them. I opened your schedule - it is apparently linked to another schedule which you didn't include.

The tasks are still all manually scheduled.

Regarding the above - all of the subtasks are manually scheduled. Do no assign the resource to the summary task - he/she should be assigned to each meeting.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
project server 2007 - project checkin failed at 37% marcoheras Project 1 07-01-2015 01:42 PM
Example for using Ms Project in construction project safaa Project 1 11-08-2012 05:54 AM
Connectivity issue of Project Professional with Project Server kashif Project 0 03-27-2009 06:37 AM
Error 9571 when opening Project Server from Project Pro mona Project 0 04-24-2007 07:50 AM
Different % complete in Project Center & View a Project mikaelbelchior Project 1 01-25-2006 12:56 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:06 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft