#15
|
|||
|
|||
![]()
Hello Margaret, sorry to bother you again but I would really like your help once more.
So I am trying to use what you have suggested and I am having a bit of problem with the starting dates that MS chooses automatically. For example: My project start date is 13 June. Pick Up Point 1 I would like it to be at 1 July. Pick Up Point 2 I would like it to be at 1 August. Pick Up Point 3 I would like it to be at 1 Sept. Phase 1 of server 1 lasts 3 days, so I have defined a 7fs-3d dependency. Task 7 has a dependency with Pick Up Point 1 milestone. So when I change the "Pick Up Point 1 milestone" date, I would expect that the starting date of phase 1 is automatically set to 3 days before the start date of task 7. However this does not happen for some servers. Any idea why? I attach my mpp. Thank you! Nantia |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
zislam14 | Project | 1 | 12-17-2015 03:58 PM |
![]() |
Rowey | Project | 5 | 05-01-2015 07:22 AM |
![]() |
Puddlerunna | Project | 9 | 11-25-2014 06:16 AM |
flag to indicate finish date does not equal baseline finish date | TCB | Project | 3 | 08-06-2014 02:49 PM |
remaining duration vs finish date | ketanco | Project | 3 | 02-17-2012 02:24 PM |